PROGRESS PHOTOS AS OF 6TH OF MARCH 2016

EXTERNAL PLASTERING FROM GF TO MEZZANINE FLOOR
CONTINUE INTERNAL BLOCK WORKS INSTALLATION AT FIRST FLOOR
COMPLETED HCS INSTALLATION AT 3RD LOOR
COLUMNS FROM 3RD FLOOR TO 4TH FLOOR AND 4TH FLOOR FORMWORKS FOR BEAMS AND SLAB ON PROGRESS
RE-BARS AND FORMWORKS FOR BEAMS AND SLAB AT 4TH FLOOR ON PROGRESS
RE-BARS AND FORMWORKS FOR BEAMS  AT 4TH FLOOR ON PROGRESS
RE-BARS AND FORMWORKS FOR BEAMS AND SLAB AT 4TH FLOOR ON PROGRESS
RE-BARS AND FORMWORKS FOR BEAMS AND SLAB AT 4TH FLOOR ON PROGRESS
EXTERNAL PAINTING  FOR SUBSTATION ON PROGRESS
EXTERNAL PAINTING  FOR SUBSTATION ON PROGRESS